1
Greater Gabbard Wind Farm Met Mast
Greater Gabbard Wind Farm Met Mast
DATE: 2013/12/21::
2
greater gabbard offshore windfarm uk
greater gabbard offshore windfarm uk
DATE: 2010/10/19::
3
Greater Gabbard offshore wind farm
Greater Gabbard offshore wind farm
DATE: 2013/08/07::
4
Severe gale conditions at the Greater Gabbard Offshore Wind Farm (24-09-2010)
Severe gale conditions at the Greater Gabbard Offshore Wind Farm (24-09-2010)
DATE: 2010/09/25::
5
ITC AHT "Typhoon" Greater Gabbard Windfarm Project
ITC AHT "Typhoon" Greater Gabbard Windfarm Project
DATE: 2011/04/20::
6
Dalby Swale on the Greater Gabbard Offshore Wind Farm
Dalby Swale on the Greater Gabbard Offshore Wind Farm
DATE: 2014/11/04::
7
Dalby Wharfe on the Greater Gabbard Offshore Wind Farm
Dalby Wharfe on the Greater Gabbard Offshore Wind Farm
DATE: 2014/11/04::
8
Greater Gabbard Wind Farm - EDSHV
Greater Gabbard Wind Farm - EDSHV
DATE: 2012/10/12::
9
GINNY LOUISE on sea trials on the Greater Gabbard Offshore Windfarm. 2.5 - 3.5m sea.
GINNY LOUISE on sea trials on the Greater Gabbard Offshore Windfarm. 2.5 - 3.5m sea.
DATE: 2012/05/04::
10
A flat calm day on the Greater Gabbard Offshore Windfarm
A flat calm day on the Greater Gabbard Offshore Windfarm
DATE: 2012/08/15::
11
RAF RESCUE EXERCISE OFFSHORE WIND FARM GREATER GABBARD.wmv
RAF RESCUE EXERCISE OFFSHORE WIND FARM GREATER GABBARD.wmv
DATE: 2011/09/26::
12
Greater Gabbard Offshore Wind farm storm
Greater Gabbard Offshore Wind farm storm
DATE: 2013/08/02::
13
Ginny Louise transiting to the Windfarm in 2m seas.
Ginny Louise transiting to the Windfarm in 2m seas.
DATE: 2012/07/26::
14
Jumbo Offshore: The Greater Gabbard Project - Transition Piece transportation and installation
Jumbo Offshore: The Greater Gabbard Project - Transition Piece transportation and installation
DATE: 2010/11/05::
15
SSE - The official opening of Greater Gabbard
SSE - The official opening of Greater Gabbard
DATE: 2013/08/07::
16
GREATER GABBARD WINDCAT THE MOVIE.wmv
GREATER GABBARD WINDCAT THE MOVIE.wmv
DATE: 2011/05/13::
17
Offshore Wind Turbine Installation - Part 1
Offshore Wind Turbine Installation - Part 1
DATE: 2010/09/29::
18
Offshore Wind Turbine Installation - Part 2
Offshore Wind Turbine Installation - Part 2
DATE: 2010/09/30::
19
Wind Farm
Wind Farm
DATE: 2014/04/02::
20
Greater Gabbard - Operations team
Greater Gabbard - Operations team
DATE: 2013/08/07::
21
Windfarm Transfer Boat
Windfarm Transfer Boat
DATE: 2012/02/18::
22
Mechanics of Wind Turbines - Offshore Farms
Mechanics of Wind Turbines - Offshore Farms
DATE: 2013/04/06::
23
Ginny Louise transiting to the Windfarm in flat calm seas
Ginny Louise transiting to the Windfarm in flat calm seas
DATE: 2012/07/26::
24
ʬ Wind Farm YouTube
ʬ Wind Farm YouTube
DATE: 2015/05/10::
25
Suffolk North Sea wind farm affects fishermen
Suffolk North Sea wind farm affects fishermen's incomes
DATE: 2014/09/04::
26
Wind farm takes shape off Fukushima as Japan seeks non-nuclear energy
Wind farm takes shape off Fukushima as Japan seeks non-nuclear energy
DATE: 2013/07/12::
27
Seajacks "5 Days with the Leviathan" Part 2 .mov
Seajacks "5 Days with the Leviathan" Part 2 .mov
DATE: 2011/12/02::
28
Wind farm
Wind farm
DATE: 2014/08/12::
29
Seajacks "5 Days with the Leviathan" Part 1 .mov
Seajacks "5 Days with the Leviathan" Part 1 .mov
DATE: 2011/12/02::
30
I
I'm SSE - Offshore wind
DATE: 2013/09/06::
31
Wind Farm
Wind Farm
DATE: 2015/06/20::
32
Wind Farm
Wind Farm
DATE: 2015/06/13::
33
AJ Woods Offshore Crane Lift
AJ Woods Offshore Crane Lift
DATE: 2012/06/08::
34
Medivac from offshore wind turbine.mp4
Medivac from offshore wind turbine.mp4
DATE: 2011/11/24::
35
MaXccess Trials
MaXccess Trials
DATE: 2013/09/01::
36
A day in the Life of Ginny Louise - Part 1
A day in the Life of Ginny Louise - Part 1
DATE: 2012/08/15::
37
WIL 2580 & The Titan
WIL 2580 & The Titan
DATE: 2009/09/30::
38
Sea Jack being towed into Harwich Harbour
Sea Jack being towed into Harwich Harbour
DATE: 2010/06/05::
39
Pushing on 2m GGOWF
Pushing on 2m GGOWF
DATE: 2012/07/06::
40
Anglia News Suffolk Soldiers 23 Engineer Regiment & Car Auction & ITV Fixers Learning Difficulties
Anglia News Suffolk Soldiers 23 Engineer Regiment & Car Auction & ITV Fixers Learning Difficulties
DATE: 2010/09/09::
41
Great Gabbard windfarm great escape :)
Great Gabbard windfarm great escape :)
DATE: 2013/09/28::
42
Crew Change Pt 2
Crew Change Pt 2
DATE: 2011/02/20::
43
GE
GE's Digital Wind Farm: Replay of our Live Reveal at Windpower 2015
DATE: 2015/05/20::
44
Greater Gabbard-Abigail Caveney
Greater Gabbard-Abigail Caveney
DATE: 2013/09/11::
45
Wind Turbine Installation Vessel-3D (Swire Pacific Offshore)
Wind Turbine Installation Vessel-3D (Swire Pacific Offshore)
DATE: 2012/12/06::
46
Mayday Array - emergency training at the world
Mayday Array - emergency training at the world's biggest offshore wind farm
DATE: 2012/11/14::
47
Njord Kittiwake - Greater Gabbard 12th Feb
Njord Kittiwake - Greater Gabbard 12th Feb '13
DATE: 2013/02/12::
48
The construction of Ormonde wind farm - Vattenfall
The construction of Ormonde wind farm - Vattenfall
DATE: 2014/11/25::
49
Wind Farm Service Vessel _ Mercurio Shipyard
Wind Farm Service Vessel _ Mercurio Shipyard
DATE: 2012/01/14::
50
Fastcat North Hoyle Offshore Wind Farm
Fastcat North Hoyle Offshore Wind Farm
DATE: 2008/03/05::
NEXT >>
RESULTS [51 .. 101]
From Wikipedia, the free encyclopedia
Jump to: navigation, search
Greater Gabbard Wind Farm
2013-02 windpark.JPG
Farm seen from a plane flying from Amsterdam to London
Greater Gabbard wind farm is located in North Sea
Greater Gabbard wind farm
Location of Greater Gabbard wind farm in the North Sea
Country England
Location Inner Gabbard and The Galloper banks
North Sea
Suffolk Coast
Coordinates 51°52′48″N 1°56′24″E / 51.88000°N 1.94000°E / 51.88000; 1.94000Coordinates: 51°52′48″N 1°56′24″E / 51.88000°N 1.94000°E / 51.88000; 1.94000
Status Operational
Commission date 2012
Owner(s) Scottish and Southern
RWE Npower Renewables
Wind farm
Distance from shore 23 km (14 mi)
Power generation
Units operational 140
Make and model Siemens Wind Power: SWT3.6-107
Nameplate capacity 504 MW
Turbines in harbour, waiting to be mounted. Red helicopter platform on top.
As seen from the Stena Line Harwich to Hook of Holland car ferry in 2014.

Greater Gabbard is a 504 MW wind farm on sandbanks 23 kilometres (14 mi) off the coast of Suffolk in England at a cost of £1.5 billion.[1] Onshore construction activities commenced in early July 2008 at Sizewell. It was completed on 7 September 2012 with all of the Siemens SWT3.6-107 turbines connected.[2]

History[edit]

The project was originally developed by Greater Gabbard Offshore Winds Limited (GGOWL) which was a joint venture between Airtricity and Fluor. Airtricity was subsequently bought by Scottish and Southern Energy who have bought out Fluor's 50% stake for £40m which is expected to cost £1.3b. Fluor are now contracted to design, supply, installation and commissioning of the balance of the plant.[3] Scottish and Southern sold a 50% stake to RWE, the owners of Npower (UK), in November 2008 for £308m.[4]

The project was given the go-ahead in May 2008 and work started in June.[5] In July 2011 erection of the turbines was two thirds complete, with all the pile foundations installed.

In October 2009 Seajacks Ltd delivered its 7,000 tonne Leviathan vessel to Fluor Ltd which sailed to Harwich to prepare the hook-up and commissioning of an in-field substation and then installation of the turbines.[6] The first foundations were installed in autumn 2009 with the first of a total of 140 turbines installed in the spring 2010.[7] Electricity generation began on 29 December 2010 and construction was completed on 7 September 2012.[2]

The wind farm may be seen by the public from the Stena Line Harwich to Hook of Holland car & passenger ferry, the route passing within a few kilometres.

Galloper extension[edit]

An extension of the project, called Galloper, was agreed in May 2013. The proposal was to add up to 140 turbines to the development, producing up to 504 MW of electricity. The wind farm was expected to be completed in 2017.[8][9] The project was being developed in partnership by RWE Innogy and SSE.[10]

In November 2013 the project capacity was reduced to 68 turbines producing 340 MW. In March 2014, SSE announced that it would be pulling out of the project.[10] In October 2014 RWE Innogy announced that it too was abandoning the project,[11] but in December the company revealed that it was still seeking potential investment partners.[12]

Greater Gabbard specifications[edit]

  • Number of turbines: 140[1][13]
  • Power rating: 504 MW[13]
  • Load factor: 39.6% (estimated)[13]
  • Estimated output: 1.75 TWh per year[13]
  • Cost: £1512 million[1] (£650 million not counting grid connection)[14]
  • Cost of grid connection: £317 million [15]
  • Location: offshore, 23 kilometres (14 mi) from Sizewell on the Inner Gabbard and The Galloper sandbanks[3]
  • Water Depth: 20m - 32m [1]

Incidents[edit]

On 12 November 2009, a man was killed and a woman injured after a chain broke and the two people were hit with pieces of the chain. Police responded to the incident, and an investigation was launched. The casualties were on board a tugboat, the Typhoon.[16]

On 21 May 2010, a man died and another suffered serious injuries following an accident at Parkeston Quay, Harwich. Per Terp, a 42-year-old Siemens engineer from Norresundby, Denmark, died in the incident. A 43-year-old German national was taken to Addenbrooke’s Hospital. The incident happened at about 7.50 am while loading a wind turbine blade on the vessel Seajack.[17][18]

In September 2013 remedial work was begun on the export cables close to shore as the cables were not buried sufficiently deeply.[19] The work which was meant to take three weeks was only finished in September 2014.[19] The work caused problems for local fishermen who asked the Greater Gabbard Offshore Wind Farm for a disruption payment.[19] A spokesman for SSE denied that the work was responsible for the snagging of fishing nets.[19]

See also[edit]

References[edit]

  1. ^ a b c Greater Gabbard 4c . Retrieved: 18 August 2010.
  2. ^ a b "Greater Gabbard completed and operational". Retrieved 28 May 2015. 
  3. ^ a b "Scottish and Southern Energy: Greater Gabbard project information". 
  4. ^ Milner, Mark (2008-11-04). "SSE sells half a North Sea windfarm for £300m". The Guardian (London). Retrieved 2010-04-02. 
  5. ^ "Greater Gabbard Wind Project Gets Go-ahead". 
  6. ^ "Arrival of Seajacks Leviathan Liftboat Marks Start of Contract at World’s Largest Offshore Wind Development". 
  7. ^ "Lowestoft wind farm project gathering pace". Lowestoft Journal. 2009-11-02. 
  8. ^ Galloper offshore wind farm gets green light, Inside Government, 2013-05-24. Retrieved 2013-07-07.
  9. ^ Suffolk coast Galloper offshore windfarm given go-ahead, BBC news website, 2013-05-24. Retrieved 2013-07-07.
  10. ^ a b "SSE maps Galloper exit route". renews. 5 September 2014. 
  11. ^ "Suffolk: Jobs blow as Galloper wind farm project is shelved". East Anglian Daily Times. 23 October 2014. 
  12. ^ "Talks could see revival of axed Galloper windfarm project". East Anglian Daily Times. 30 December 2014. 
  13. ^ a b c d "Greater Gabbard Offshore Wind Farm". Retrieved 28 May 2015. 
  14. ^ Greater Gabbard Offshore Wind Project, United Kingdom Power Technology. Retrieved: 10 November 2010.
  15. ^ "Balfour Beatty plc - News & views - News - Balfour Beatty reaches financial close for the £317m Greater Gabbard OFTO (27 November, 2013)". Retrieved 28 May 2015. 
  16. ^ "Harwich: Tragedy at wind farm site". Harwich and Manningtree Standard. 2009-11-13. 
  17. ^ "Fatal incident at Harwich Port". Essex Police. 
  18. ^ Fatal accident in Harwich vertikal.net, 21 May 2010. Retrieved: 18 August 2010.
  19. ^ a b c d "Suffolk: Fishermen’s concerns due to be raised at wind farm meeting today". East Anglian Daily Times. 2 September 2014. 

External links[edit]

Wikipedia content is licensed under the GFDL License
Powered by YouTube
MASHPEDIA
LEGAL
  • Mashpedia © 2015